Home > City Centre campus > When will it happen?
When will it happen?
- June 2008 – Outline Planning Application submitted
- August 2008 – Consultant team (architects, engineers etc.) appointed.
- September 2008 – On-site archaeological investigations commence.
- December 2008 – Detailed (reserved matters) planning applications submitted.
- May to November 2009 – Site enabling works (services diversions; remediation etc) take place.
- March 2010 to September 2011 – Main building contract(s) take place – construction of building “envelope”
- September 2011 to May 2012 – Interior and specialist fit-out works contracts take place.
- May & June 2012 – Birmingham City University specialist equipment installed.
- June – September 2012 – Faculties migrate to first phase of new building.
- 17 September 2012 – New academic year starts.
|